Rim Rock Wind Farm achieves commercial operation

A wind turbine

A Rim Rock Turbine generates energy in Montana. (Photo by NaturEner)

Western’s Connections blog first shared that the Rim Rock Wind Farm’s planned to interconnect through the Montana Alberta Tie Limited transmission line (a project supported through Western’s Transmission Infrastructure Program) in a post last Jan. 10, 2012. Even though Western’s involvement with MATL was completed last fall, the wind farm announced another milestone yesterday.

NaturEner publicized Jan. 10 that the commercial operations of its Rim Rock Wind Farm near Kevin, Mont., started Dec. 28, 2012. Read more »

NaturEner holds ceremony for Rim Rock wind farm in Montana

Rim Rock wind turbine

Rim Rock wind turbine owned and operated by NaturEner (Photo provided by NaturEner website)

Hundreds of people attended NaturEner’s opening ceremony Sept. 14 for the Rim Rock wind farm just north of Cut Bank, Mont., to celebrate overcoming the considerable challenges in making the wind farm a reality.

“There was a time last summer when we were doubtful we were going to be able to pull this off,” said Greg Copeland, Development Director of the U.S. division of the Spanish-owned NaturEner. Read more »

Enbridge takes up MATL line construction

Renewable Energy Systems Americas employees continue work on the MATL line Jan. 12 near Sweetgrass, Mont. (Photo courtesy of Enbridge)

Taking another step toward bringing renewable energy to market, this month contractors got back to work on the Montana Alberta Tie Limited project.

After receiving a notice to proceed on construction Jan. 10, Renewable Energy Systems Americas employees, hired by Enbridge, got boots on the ground quickly and began remediation work on some existing structures and line near Sweetgrass, Mont.

With 60 percent of the transmission line and substations already completed, Enbridge and RES are continuing to make progress on the line north of Marias River.

Funded partially through Western Area Power Administration’s Transmission Infrastructure Program, Enbridge expects to complete the 214-mile, 230-kilovolt line in 2012.

“Enbridge is committed to quality construction of the line and timely completion of the project,” said Vi Michaelis, Western’s project manager for MATL. “We are very encouraged by the construction restart.”

Once completed, MATL will interconnect the 189-megawatt Rim Rock wind power project, which announced its notice to proceed on construction Jan. 9.

Rim Rock wind project to interconnect through MATL

On Jan. 9, NaturEner announced its plans to construct the Rim Rock wind power project, which will bring 189 megawatts of renewable energy online through the Montana Alberta Tie Limited project.

NaturEner secured a $320 million construction loan with Morgan Stanley Jan. 9, putting the project on track to be commercially operational by the end of 2012. With the MATL line expected to be placed into service in 2012, Rim Rock will have the transmission access it needs to deliver renewable energy.

“The strong financial backing of the U.S. Department of Energy, carried out through Western, has enabled MATL which, together with incentives such as the Production Tax Credit, has allowed Rim Rock to proceed,” added Jose M Sanchez-Seara, CEO of NaturEner. “We greatly appreciate the U.S. Government’s support for renewable energy generation and the transmission lines that allow them to deliver the energy to markets across North America.”

Rim Rock is a 189-MW wind farm project located in Glacier and Toole Counties, Mont., that will consist of 126 Acciona AW-77 1.5 MW turbines. The project area encompasses about 21,000 acres of private land. The project is expected to generate enough energy to power more than 60,000 homes and will offset more than 389,000 metric tons of CO2 emissions per year.