Posts tagged: Montana

Lovell-to-Yellowtail project checks halfway point

Lovell-to-Yellowtail Phase II

A contractor works on an H-frame structure along the Lovell-to-Yellowtail No. 1 transmission line, or LV-YT No. 1, June 26, 2013. (Photo by Ryan Sharp)

Construction work on the two Lovell-to-Yellowtail transmission lines, which run between Lovell, Wyo., and Yellowtail Dam, Mont., continues to progress according to schedule.

The dual 94-mile, 115-kilovolt lines that carry power from Yellowtail Dam in Montana are undergoing a badly needed rebuild as many of their components can trace their origins to their construction in 1956 and 1966 by the Bureau of Reclamation.  

“Many of the existing poles are in immediate need of replacement,” said Rocky Mountain Project Manager Travis Anderson.

The project is in the middle of the second phase, which includes rebuilding about 16 miles of each line that run both north and south of the National Park Service Big Horn National Recreation Area and Crow Reservation. Read more »

T-line construction continues even in winter

When you think of Wyoming and Montana in the winter, you might think “cold”—cold enough that you wouldn’t want to be outdoors working on the construction of a transmission line. But that’s exactly what Western crews will be doing this winter.

Western contractor operating the hydraulic press, right, with another crew member as his assistant to perform dead-ending operations as part of Phase 1 of the Lovell-to-Yellowtail transmission line rebuild project.

Western contractor operating the hydraulic press, right, with another crew member as his assistant to perform dead-ending operations as part of Phase 1 of the Lovell-to-Yellowtail transmission line rebuild project.

Crews recently wrapped up rebuilding the Lovell-to Yellowtail No. 1 and No. 2 115-kilovolt transmission lines in the Big Horn Canyon National Recreation Area in Wyoming and Montana. They expect to begin reclamation of unneeded access roads soon. In Feb. 2013, they will begin rebuilding the sections of the lines north and south of the NRA.

The Lovell-to-Yellowtail transmission lines are located between Lovell, Wyo., and Yellowtail Dam, Mont., and help provide the reliable transmission of Yellowtail Dam’s generation.

You can see more photos of Phase 1 construction on Flickr.

NaturEner holds ceremony for Rim Rock wind farm in Montana

Rim Rock wind turbine

Rim Rock wind turbine owned and operated by NaturEner (Photo provided by NaturEner website)

Hundreds of people attended NaturEner’s opening ceremony Sept. 14 for the Rim Rock wind farm just north of Cut Bank, Mont., to celebrate overcoming the considerable challenges in making the wind farm a reality.

“There was a time last summer when we were doubtful we were going to be able to pull this off,” said Greg Copeland, Development Director of the U.S. division of the Spanish-owned NaturEner. Read more »

Montana wind farm completes 11 wind turbines

NaturEner reported it completed installation of 11 turbines as of July 3 on the southwest part of the Rim Rock Wind Farm, Mont.

Several stakeholders, including Western representatives, toured the Rim Rock site the last week of June to see the construction progress. The wind farm will be interconnected through the Montana-Alberta Tie Limited transmission line project.

You can see additional photos and read more about the project’s construction and environmental progress on NaturEner’s website.

Enbridge takes up MATL line construction

Renewable Energy Systems Americas employees continue work on the MATL line Jan. 12 near Sweetgrass, Mont. (Photo courtesy of Enbridge)

Taking another step toward bringing renewable energy to market, this month contractors got back to work on the Montana Alberta Tie Limited project.

After receiving a notice to proceed on construction Jan. 10, Renewable Energy Systems Americas employees, hired by Enbridge, got boots on the ground quickly and began remediation work on some existing structures and line near Sweetgrass, Mont.

With 60 percent of the transmission line and substations already completed, Enbridge and RES are continuing to make progress on the line north of Marias River.

Funded partially through Western Area Power Administration’s Transmission Infrastructure Program, Enbridge expects to complete the 214-mile, 230-kilovolt line in 2012.

“Enbridge is committed to quality construction of the line and timely completion of the project,” said Vi Michaelis, Western’s project manager for MATL. “We are very encouraged by the construction restart.”

Once completed, MATL will interconnect the 189-megawatt Rim Rock wind power project, which announced its notice to proceed on construction Jan. 9.