Posts tagged: Lovell-to-Yellowtail

Lovell-to-Yellowtail transmission line rebuild Phase 2 update

Insulation is being used to isolate the wire in the air from the equipment on the ground, as part of Phase II of the Lovell-to-Yellowtail transmission line rebuild project, March 26, 2013

Contractors continue rebuilding two 115-kilovolt transmission lines as part of Phase II of the Lovell-to-Yellowtail project. With work in the Big Horn Canyon National Recreation Area complete in fall 2012, the construction contractor started removing the No. 2 line south of the NRA in Wyoming, March 25, 2013.

Crews have about 10 miles of the No. 2 line down and are working on setting new structures in cultivated fields before irrigation of farm land begins.

While crews work on the No. 2 line, the Lovell-to-Yellowtail No. 1 transmission line continues to deliver power from Yellowtail Dam.

The upgrades to the Lovell-to-Yellowtail transmission lines No. 1 and 2 are needed to replace the original lines built by the Bureau of Reclamation in 1956 and 1966.

You can see more photos of the project’s construction on Flickr.

T-line construction continues even in winter

When you think of Wyoming and Montana in the winter, you might think “cold”—cold enough that you wouldn’t want to be outdoors working on the construction of a transmission line. But that’s exactly what Western crews will be doing this winter.

Western contractor operating the hydraulic press, right, with another crew member as his assistant to perform dead-ending operations as part of Phase 1 of the Lovell-to-Yellowtail transmission line rebuild project.

Western contractor operating the hydraulic press, right, with another crew member as his assistant to perform dead-ending operations as part of Phase 1 of the Lovell-to-Yellowtail transmission line rebuild project.

Crews recently wrapped up rebuilding the Lovell-to Yellowtail No. 1 and No. 2 115-kilovolt transmission lines in the Big Horn Canyon National Recreation Area in Wyoming and Montana. They expect to begin reclamation of unneeded access roads soon. In Feb. 2013, they will begin rebuilding the sections of the lines north and south of the NRA.

The Lovell-to-Yellowtail transmission lines are located between Lovell, Wyo., and Yellowtail Dam, Mont., and help provide the reliable transmission of Yellowtail Dam’s generation.

You can see more photos of Phase 1 construction on Flickr.