Lovell-to-Yellowtail project checks halfway point

Lovell-to-Yellowtail Phase II

A contractor works on an H-frame structure along the Lovell-to-Yellowtail No. 1 transmission line, or LV-YT No. 1, June 26, 2013. (Photo by Ryan Sharp)

Construction work on the two Lovell-to-Yellowtail transmission lines, which run between Lovell, Wyo., and Yellowtail Dam, Mont., continues to progress according to schedule.

The dual 94-mile, 115-kilovolt lines that carry power from Yellowtail Dam in Montana are undergoing a badly needed rebuild as many of their components can trace their origins to their construction in 1956 and 1966 by the Bureau of Reclamation.  

“Many of the existing poles are in immediate need of replacement,” said Rocky Mountain Project Manager Travis Anderson.

The project is in the middle of the second phase, which includes rebuilding about 16 miles of each line that run both north and south of the National Park Service Big Horn National Recreation Area and Crow Reservation. Read more »