Posts tagged: Enbridge

NaturEner holds ceremony for Rim Rock wind farm in Montana

Rim Rock wind turbine

Rim Rock wind turbine owned and operated by NaturEner (Photo provided by NaturEner website)

Hundreds of people attended NaturEner’s opening ceremony Sept. 14 for the Rim Rock wind farm just north of Cut Bank, Mont., to celebrate overcoming the considerable challenges in making the wind farm a reality.

“There was a time last summer when we were doubtful we were going to be able to pull this off,” said Greg Copeland, Development Director of the U.S. division of the Spanish-owned NaturEner. Read more »

Enbridge takes up MATL line construction

Renewable Energy Systems Americas employees continue work on the MATL line Jan. 12 near Sweetgrass, Mont. (Photo courtesy of Enbridge)

Taking another step toward bringing renewable energy to market, this month contractors got back to work on the Montana Alberta Tie Limited project.

After receiving a notice to proceed on construction Jan. 10, Renewable Energy Systems Americas employees, hired by Enbridge, got boots on the ground quickly and began remediation work on some existing structures and line near Sweetgrass, Mont.

With 60 percent of the transmission line and substations already completed, Enbridge and RES are continuing to make progress on the line north of Marias River.

Funded partially through Western Area Power Administration’s Transmission Infrastructure Program, Enbridge expects to complete the 214-mile, 230-kilovolt line in 2012.

“Enbridge is committed to quality construction of the line and timely completion of the project,” said Vi Michaelis, Western’s project manager for MATL. “We are very encouraged by the construction restart.”

Once completed, MATL will interconnect the 189-megawatt Rim Rock wind power project, which announced its notice to proceed on construction Jan. 9.

Acquisition of Tonbridge Power Inc. complete

The Montana Alberta Tie Limited Project’s parent company, Tonbridge Power Inc., announced on Oct. 13 that the acquisition of Tonbridge by an affiliate of Enbridge Inc. is a 100 perecent completed. This agreement must follow a court-approved plan. Enbridge will continue MATL’s construction and development, working closely with Western’s Transmission Infrastructure Program. MATL’s expected completion date remains around mid-2012. For more information on the acquisition visit MATL’s website.