Lovell-to-Yellowtail transmission line rebuild Phase 2 update

Insulation is being used to isolate the wire in the air from the equipment on the ground, as part of Phase II of the Lovell-to-Yellowtail transmission line rebuild project, March 26, 2013

Contractors continue rebuilding two 115-kilovolt transmission lines as part of Phase II of the Lovell-to-Yellowtail project. With work in the Big Horn Canyon National Recreation Area complete in fall 2012, the construction contractor started removing the No. 2 line south of the NRA in Wyoming, March 25, 2013.

Crews have about 10 miles of the No. 2 line down and are working on setting new structures in cultivated fields before irrigation of farm land begins.

While crews work on the No. 2 line, the Lovell-to-Yellowtail No. 1 transmission line continues to deliver power from Yellowtail Dam.

The upgrades to the Lovell-to-Yellowtail transmission lines No. 1 and 2 are needed to replace the original lines built by the Bureau of Reclamation in 1956 and 1966.

You can see more photos of the project’s construction on Flickr.