Category: Transmission work

One in a million: Western restores power quickly to Cody, Wyo., Feb. 23

Western’s line crew from the Cody maintenance shop string new cable on the Big George-to-Glendale Tap 69-kV line after a winter storm took down the line Feb. 23, causing an outage in northwest Wyoming.

On the surface, the outage that affected northwest Wyoming at about 9:10 a.m. Feb. 23 seems straight forward: A winter storm took down a 69-kilovolt transmission line north of Cody near the Park County Regional Landfill, thrusting the local utilities and the residents of Cody, Powell, Willwood, Garland and Ralston into darkness for nearly two hours.

Power was restored at about 10:50 a.m., but it wasn’t because the downed line was back on the towers.

The evening before, another event about 60 miles away from the downed line, probably caused by wind swinging the cables, called conductors, too close together on the Lovell-to-North Cody 69-kV transmission line, cut off the back-up power feed to the area through the Lovell Substation. This problem left the Big George-to-Glendale Tap 69-kV line the only power source in the area.

 “This was a one in a million deal for us,” said Cody Field Manager Doug Padgett, who responded to the Lovell Substation. “You had two separate, distinct problems caused by two separate, distinct events. It was not expected at all.”

Check out the full story on how Western and the local community worked together to restore power in Wyoming at Western’s Newsroom.

Western Administrator speaks at local Tribal Leader Forum

Western Area Power Administrator Tim Meeks spoke in Denver, Colo., Feb. 7, at the Tribal Leader Forum “Exploring the Business Link Opportunity: Transmission and Clean Energy Development in the West.”

The forum, sponsored by the Department of Energy and the second in a series of events, provided an opportunity for tribal leaders to interact with industry and Federal leaders, get information about transmission development in the West and learn about the latest trends in financing clean energy projects.

Meeks focused his remarks on transmission expansion in the West and its impact on tribal land and shared, “When you look at our service area, we’re neighbors. We need this partnership, and we need to continue to work together.”

See the news release for more information.

Western helps neighboring utility overcome storm damage

Lineman Ryan Wheeler from Western’s Redding maintenance office uses a hot stick to remove snow from a transmission line.

Lineman Ryan Wheeler from Western’s Redding maintenance office uses a hot stick to remove snow from a transmission line.

A Western Sierra Nevada line crew heeded a call for mutual aid and assistance from a neighboring utility and customer Jan. 20 in response to the unexpectedly severe Pacific Northwest winter storm, which had extensively damaged the utility’s local transmission system.

Western’s Sierra Nevada Region Redding line crew worked closely with linemen from Trinity Public Utilities District along steep and rugged terrain Jan. 20 through 22 to restore power to the citizens of Weaverville, Douglas City, Lewistown and Hayfork in northern California, or about 8,000 citizens.

Read more at Western’s Newsroom.

Planning reliable power delivery for the future

Recently, the Western’s Desert Southwest Region updated its 10-year Capital Program. The Fiscal Year 2012 Capital Program provides both a capital investment plan, as well as a funding plan, that will ensure reliable power delivery to Western’s customers.

The updated program booklet clearly describes DSW’s strategy to construct and repair Western’s transmission lines; it entails DSW’s current goals and challenges to maintain reliability and outlines its major accomplishments for FY 2011; it also provides an opportunity for customer collaboration.

Program aligns Western’s, customers’ goals

The Capital Program is an ongoing project revised annually in response to approved funding allocations for the budget year, changes in project priority, unforeseen problems with the transmission system, mandates or regulatory requirements and new contractual requirements.

Fluctuations in funding make it difficult to plan which projects to carry out and at what pace to complete them. Appropriated funds don’t carry over from year to year, which means any excess funding that is still available at the end of the fiscal year cannot be used in subsequent years.

In FY 2010, Western and its customers decided that the best way to address the ongoing funding struggle was to use prepayment funding for selected construction projects, and it has significantly helped DSW’s position. Customers prepay for transmission services, providing a source of funds to cover some of the appropriations shortfalls. Projects that are proposed for pre-payment are first submitted for funding through the typical appropriated funding process.

The use of pre-payment funding is beneficial to both Western and its customers and has provided a significant, and consistent, source of construction dollars since its inception.

Projects see 2011 success, 2012 schedules

Despite appropriated funding issues in FY 2011, DSW completed several construction and RRAD projects. “DSW customers are very satisfied with our progress, particularly in the last two years since we’ve been working prepayment projects. DSW customers are able to see their money at work and that helps build our credibility as an organization and develops a relationship of trust and  cooperation,” said Project Manager Chris Lyles.

With FY 2012 already in progress, all projects scheduled for execution this year are dependent on the receipt of adequate appropriated funding in a timely manner.

The 10-year Capital Program is the means for identifying, prioritizing, scheduling and funding projects that directly affect Western and its customers. It is essential to meeting Western’s mission of providing reliable power to its customers.

Learn more about DSW’s 10-year Capital Plan.

Enbridge takes up MATL line construction

Renewable Energy Systems Americas employees continue work on the MATL line Jan. 12 near Sweetgrass, Mont. (Photo courtesy of Enbridge)

Taking another step toward bringing renewable energy to market, this month contractors got back to work on the Montana Alberta Tie Limited project.

After receiving a notice to proceed on construction Jan. 10, Renewable Energy Systems Americas employees, hired by Enbridge, got boots on the ground quickly and began remediation work on some existing structures and line near Sweetgrass, Mont.

With 60 percent of the transmission line and substations already completed, Enbridge and RES are continuing to make progress on the line north of Marias River.

Funded partially through Western Area Power Administration’s Transmission Infrastructure Program, Enbridge expects to complete the 214-mile, 230-kilovolt line in 2012.

“Enbridge is committed to quality construction of the line and timely completion of the project,” said Vi Michaelis, Western’s project manager for MATL. “We are very encouraged by the construction restart.”

Once completed, MATL will interconnect the 189-megawatt Rim Rock wind power project, which announced its notice to proceed on construction Jan. 9.

Rim Rock wind project to interconnect through MATL

On Jan. 9, NaturEner announced its plans to construct the Rim Rock wind power project, which will bring 189 megawatts of renewable energy online through the Montana Alberta Tie Limited project.

NaturEner secured a $320 million construction loan with Morgan Stanley Jan. 9, putting the project on track to be commercially operational by the end of 2012. With the MATL line expected to be placed into service in 2012, Rim Rock will have the transmission access it needs to deliver renewable energy.

“The strong financial backing of the U.S. Department of Energy, carried out through Western, has enabled MATL which, together with incentives such as the Production Tax Credit, has allowed Rim Rock to proceed,” added Jose M Sanchez-Seara, CEO of NaturEner. “We greatly appreciate the U.S. Government’s support for renewable energy generation and the transmission lines that allow them to deliver the energy to markets across North America.”

Rim Rock is a 189-MW wind farm project located in Glacier and Toole Counties, Mont., that will consist of 126 Acciona AW-77 1.5 MW turbines. The project area encompasses about 21,000 acres of private land. The project is expected to generate enough energy to power more than 60,000 homes and will offset more than 389,000 metric tons of CO2 emissions per year.

Western works with Crow Creek Nation to repair structure

The initial topsoil removal and cutting back of the bank (notice the eroded area close to the structure footing), while Crow Creek Nation archaeological monitor looks on.

In May, floodwaters engulfed the Crow Creek Reservation located in central South Dakota, damaging several roads and struc­tures. Flash flooding eroded a ravine next to one of Western’s transmission towers located on private land within the reserva­tion boundary. The erosion endangered both the tower and the line’s operability and reliability near a 230-kilovolt steel transmission line. Had the bank caved to the edge of the footing, the tower would have begun to lean and could eventually have collapsed, cutting power to the customers who rely on the line. Western’s Upper Great Plains region employees, in cooperation with the Crow Creek Nation, worked to prevent its destruction.

Western’s Engineering and Maintenance employ­ees determined that the best way to fix the erosion problem was to use simple but effective Gabion baskets to stabilize the bank and divert water away from the structure. Gabion baskets are large wire baskets filled with rip-rap and connected together—in this instance, three tiers high— to divert the flow of water away from an eroding bank. Initially, the floor of the ravine was leveled in order for a track-hoe to cut back the bank for the placement of the baskets. Filter fabric that allows for the pas­sage of water, but not sediment, was layered between the baskets, and the soil from the excavated bank was then filled in behind the baskets. A layer of clay was then placed in the ravine in front of the baskets to prevent soil from eroding out from underneath.

The Crow Creek Nation, as stewards of the cultural resources within the reservation boundar­ies, felt that it was important to protect and preserve these sites. It’s also Western policy to preserve, protect and avoid disturbance to cultural resources whenever possible. For that reason, UGP developed several project alternatives to address the emer­gency situation without damaging the archaeological sites. Western was able to keep its construction “footprint” to a minimum, thereby reducing the amount of ground disturbance around the project area.

Field work began Nov. 2 and concluded within two weeks. Nice weather condi­tions helped the work progress quickly. Following completion of the project, Western restored the excavated bank and reintroduced the removed vegetation to the topsoil so that it has a chance to recover in spring.

Western wins APPA 2011 Annual Report Contest award

Ingenuity and creativity in copy, design, financial data, graphics and communicating the agency’s special story earned Western the American Public Power Association’s Award of Merit for Western’s Fiscal Year 2010 Annual Report.

On Wednesday, Annual Report Project Manager Jennifer Neville accepted the award on behalf of Western during the APPA Customer Connections Conference in Savannah, Ga. “I feel honored that our efforts to support our customers and to communicate on a level that matches their style is being recognized,” Neville remarked. 

The APPA award is the first that Western’s annual reports have received. Neville believes that the report was selected due to its different visual look and style. “This is the first year that we have used a graphical, painted theme rather than photographs,” Neville explained. “Once we devised the theme, Roadmap for Renewable Energy, Graphical Designer, Grant Kuhn, came up with designs, and this one was the clear choice by Senior Managers.”

Read more on Western’s website.

Acquisition of Tonbridge Power Inc. complete

The Montana Alberta Tie Limited Project’s parent company, Tonbridge Power Inc., announced on Oct. 13 that the acquisition of Tonbridge by an affiliate of Enbridge Inc. is a 100 perecent completed. This agreement must follow a court-approved plan. Enbridge will continue MATL’s construction and development, working closely with Western’s Transmission Infrastructure Program. MATL’s expected completion date remains around mid-2012. For more information on the acquisition visit MATL’s website.

Bill to repeal TIP’s borrowing authority moves to full House

House Resolution 2915, which proposes to repeal Western’s Transmission Infrastructure Program’s $3.25 billion borrowing authority from the U.S. Treasury, passed the House of Representatives Committee of Natural Resources with no amendments Oct. 5 with a 26-17 straight party-line vote.

While the three projects currently approved to use the borrowing authority – TransWest Express (development phase), Electrical District 5 – Palo Verde Hub and the Montana Alberta Tie, Limited – would not be impacted by the bill’s passage, no other projects being considered would receive funding.

“New transmission is urgently needed in the western United States.  And yet, getting lines in the air has been far too slow over the past few decades,” said Lauren Azar, senior advisor to U.S. Energy Secretary Steven Chu, in a written testimony for a Sept. 22 hearing with the Subcommittee on Water and Power. “Western’s $3.25 billion of permanent, indefinite, borrowing authority is, therefore, a critical tool for addressing two of the major energy challenges we now face in the West — the need for additional transmission infrastructure and integration of renewables onto the grid.”

The bill will now be considered in the full House.

TIP’s borrowing authority constructs or upgrades transmission infrastructure within Western’s 15-state service area that has the reasonable expectation of helping deliver renewable generation to customers and is in the public interest.