Category: Transmission work

BLM releases Southine EIS scoping report

The Bureau of Land Management recently released the scoping summary report for the proposed Southline Transmission Line project, ending the 90-day scoping period for the project environmental impact statement.

BLM and Western, as joint lead agencies in the preparation of the EIS, held six open houses in New Mexico and Arizona in May during the scoping phase. The scoping phase gives the public the opportunity to learn about a proposed project, share concerns and provide comments on what potential impacts should be analyzed in the draft EIS expected in 2013.

Major concerns discovered during the scoping process included the NEPA process and BLM’s management plan amendment, wildlife impacts and socioeconomic impacts.

Southline Transmission, LLC, proposes to construct, operate and maintain a 360-mile, high-voltage power line from Afton, N.M., to Saguaro substation northwest of Tucson, Ariz. About 240 miles would be new construction of a 345-kilovolt line on mostly BLM land while the rest would be an upgrade to an existing Western line. If completed, the line will add 1,000 megawatts of transmission capacity to the southwest.

Western conducted grid reliability webinar

Western Area Power Administration conducted a Grid Reliability—Impacts to Tribal Renewable Projects webinar in partnership with the U.S. DOE Office of Indian Energy Policy and Programs and DOE Tribal Energy Program July 25.

About 55 Tribal members and interested parties participated in the webinar with 112 registering for the event. Western’s Reliability Compliance Program Manager was the featured speaker, covering topics such as key definitions, reliability organizations, oversight process, standards and enforcement among other reliability considerations. 

Western’s Renewable Resource Program Manager Randy Manion shared, “This webinar was the eighth in the Fiscal Year 2012 Tribal Webinar series coordinated by Western. Laurent Weber, Western’s Reliability Compliance Program manager, did a masterful job explaining complex issues.”

The webinar series is giving Western transmission and power marketing experts a platform to share their incredible knowledge and expertise with Tribal representatives, renewable energy developers and other important stakeholders.

Reclamation delays project to relocate Western lines

On July 31, the Bureau of Reclamation announced the delay of a project to relocate Western’s high-voltage transmission lines near Yellowtail Dam in Montana from August to October because of increased environmental concerns.

“I applaud our hydropower partners at Western for their sensitivity to the potential ramifications of the outage associated with the relocation project,” said Dan Jewell, Area Manager for Reclamation’s Montana Area Office. “While these types of maintenance events are never risk-free, delaying the work until later in the year will help reduce that risk.”

The current location of the lines puts them at risk for the dangerous ice storms that occur in the area over winter, prompting a joint effort between Reclamation and Western to move the lines.

The relocation is scheduled to take about two weeks, and the outage requires Reclamation to bypass the water turbines. With the unusually warm summer and fall, agencies and environmentalists were concerned about the impact of not using the colder water at deeper water levels to power the turbines in August. Alternatives to move the water, including the holo-jets and spillways, could increase nitrogen or water temperature, potentially harming fish.

According to Friends of the Bighorn River blog, “With lake water temperatures already well into the 70′s, a slight mistake, miscalculation or unplanned natural or man-made event could have long lasting, devastating effects on the river where fish are already highly stressed from anglers, low flows, gas bubble trauma, irrigation return, warm water and habitat loss.”

 The delay is thought to be a fitting compromise to ensure reliable electricity from Yellowtail Dam this winter and protection of the environment.

Western “defines the future”

Western recently published new webpages to publicize progress toward the objectives in Secretary of Energy Stephen Chu’s March 16 memo to the power marketing administrations.

The webpages advertise public involvement opportunities, including stakeholder meetings, and show how Western is progressing toward meeting the memo’s objectives.

While Western calls the section “Defining the future,” the agency remains committed to providing reliable, cost-based electric service to its preference power customers. The objectives in the PMA memo only call for Western’s leadership in “transforming our electric system to the 21st century to ensure our nation remains competitive in a global economy,” as Secretary Chu stated in his May 30 blog post.

“[Western] has an enormous opportunity to assume a leadership role in helping prevent future blackouts by making the organizational and operational changes necessary to enhance overall system operations and planning,” he added.

Be sure to check out the pages regularly as they will be frequently updated with more information through the end of the year.

Southline project scoping period extended to July 5

As a result of numerous requests, the Bureau of Land Management is extended the scoping period for the proposed Southline Transmission Line Project. The scoping period, which was scheduled to end June 4, has been extended to end July 5. Western is a co-lead agency on the environmental impact statement.

The Southline Transmission Project would collect and deliver electricity across southern New Mexico and southern Arizona, relieving congestion, strengthening the existing electrical system and improving transmission access for local renewable and other energy sources.

Learn more about the project on BLM’s webpage.

Energy Secretary elaborates on PMA memo

Today, Energy Secretary Stephen Chu published on the Department of Energy blog about the PMA memo he released March 16. In it, he further describes what the memo is intended to do and the next steps Western will take in gathering stakeholder input.

“Earlier this year, I called on our Nation’s Power Marketing Administrations (PMAs) to help lead the 21st century transformation of our nation’s electricity sector to better protect our economic and national security. As this process gets underway, the Department of Energy will work in close collaboration with each PMA to solicit the critical on-the-ground input vital to achieving this goal in the best manner possible. I look forward to working with all interested parties in every PMA region to meet this shared objective,” said Secretary Chu.

Click to read the entire blog post.

Tribal webinar to discuss today’s energy needs, yesterday’s grid

Western Area Power Administration, the U.S. DOE Office of Indian Energy Policy and Programs, and the DOE Tribal Energy Program are offering a free, informative webinar and discussion May 30 on how utilities’ generation portfolios are changing, often faster than the grid infrastructure that supports it, and the challenges currently being faced to integrate new generation and demand (load) response technologies into a grid that was designed to operate a different way.

There is no charge to attend the webinar; however, you must register to participate.

Tribal utility managers and resource engineers will hear information on (1) key findings in the MIT Energy Initiative Report on the changes needed in the U.S. transmission grid to handle expected challenges such as the influx of electric cars and wind and solar generation and (2) the Western Grid Group’s Clean Energy Vision Project, which charts a sustained, orderly transition from the carbon intensive electricity system of today to a cleaner, smarter and healthier electricity system of the future.

The webinar is chaired by Jay Caspary, with Southwest Power Pool and on assignment to the DOE Office of Electricity Delivery and Energy Reliability. The two speakers are Dr. Richard Schmalensee and Dr. Carl Linvill.

Dr. Schmalensee is the Director of the MIT Center for Energy and Environmental Policy Research at the MIT Sloan School of Management. Dr. Schmalensee was co-chair of the recent MIT Energy Initiative report on The Future of the Electric Grid. Dr. Linvill is Director of Integrated Energy Analysis and Planning with Aspen Environmental Group and a member of the Western Grid Group. He is a major contributor to the Clean Energy Vision Project.

For more information on this and the other tribal webinars, visit http://www.repartners.org/#tribeseries.

Western holds Tribal webinar on transmission policy

Western conducted an Unwinding Transmission Policies webinar for 30 Native American Tribes and other interested parties Feb. 29 to explain what transmission policy is, how it is established and who enforces it. FERC Order 1000 and its possible impact to transmission resources were also discussed.

Questions ranged from whether Western would be releasing a renewable request for proposals to very specific issues regarding FERC policy.

“[It] was a well-done presentation. I appreciated [the speaker]’s organized and thoughtful approach to such a complex topic,” said Jan Bush, an environmental planner at Transcon Environmental. “When the recorded presentation becomes available, I would like to share it with the environmental planning staff here at Transcon.

This is the fourth webinar Western has held in partnership with the DOE Office of Indian Energy Policy and Programs and the DOE Tribal Energy Program.

Check out more, including audio recordings and presentations, in Western’s press release.

Western, UWIG wind, solar workshop imparts interconnection knowledge

Thirty five utility groups, grid operators and renewable energy developers filled the Western Area Power Administration’s Electric Power Training Center in Golden, Colo., Feb. 22 to 24 to learn about interconnecting wind and solar energy into the bulk and distribution electric grid.

“I thought it was great. It was a nice forum with impressive speakers,” said Jay Caspary from the Department of Energy Office of Electricity Delivery and Energy Reliability and on loan from the regional transmission organization Southwest Power Pool. “There were a lot of smart people there, and I enjoyed connecting with people in the area.”

Find out more at Western’s press release.

DSW makes power lines more visible to protect wildlife

Seeing a flock of birds on a transmission line can be an amazing sight, and although birds can perch safely on electrical wires, colliding with them can cause injury or death. When power lines are near lakes and ponds, the risk of collision increases. This is the case of the birds of Lake Watson in Prescott, Ariz.

Desert Southwest Apprentice Lineman Horacio Adriano installs bird diverters on Western’s Prescott-Pinnacle Peak 230-kilovolt line.

Desert Southwest Apprentice Lineman Horacio Adriano installs line-marking devices on Western’s Prescott-Pinnacle Peak 230-kilovolt line.

In January, a five-man Desert Southwest maintenance crew, led by Foreman II Lineman Ronnie Martinez, installed line-marking devices, or LMDs, on Western’s Prescott-to-Pinnacle Peak 230-kilovolt line. “This is the first time DSW Maintenance crews took on a project like this so it was a good experience for all involved,” said Line Crew Foreman III Mark DePoe.

DSW installed the LMDs because residents of Lake Watson were worried that the birds using the lake were colliding with the overhead ground wires, and asked Western to help. Although there was no evidence of bird collisions near the lines, DSW’s Environmental group decided to install the devices. “Our power lines run east and west in that area and pass just southwest of the lake. Although we haven’t seen bird causalities in the area, we agreed to install the LMDs before anything hap-pened. We pride ourselves on being good neighbors and environmental stewards,” explained DePoe.

Before installation, the line was de-energized, and crew members thoroughly inspected the overhead ground wires for damage as a safety precaution. ἀe devices are staggered 50 feet apart  on each of the overhead ground wires.

DSW installed LMDs that clamp onto overhead ground wires. They are made of light plastic and reflective tape so they can easily swivel in the wind, and since they are not stationary, they are more likely visible to birds. “The birds will see [the devices] and not collide with the overhead ground wires,” said DePoe.

Although Lake Watson residents have not experienced an outage from bird collisions on the Prescott-to-Pinnacle Peak line, animals are one of the main causes of power outages in Western’s territory. Biologist Misti Schriner shared, “Western is actively involved in Avian Power Line Interaction Committee efforts to under-stand and educate the utility industry and conservation groups about the nature of power lines and birds.”

Western’s proactive approach to the situation, coupled with the collaborative effort between Maintenance, Environment and the community, created a win-win situation for everyone.