Category: Renewables

Next Tribal webinar, May 29, highlights transmission issues

The Electric Reliability Council of Texas and the eight U.S. regional reliability organizations are expanding regional transmission planning activities and broadening stakeholder involvement to plan for East-West interconnections. Hear about the status of the organizations’ plans and evaluations of long-term regional transmission needs.

Register today for Regional Transmission Planning, fifth webinar in the free series, Turning Knowledge into Energy Projects. All webinars in the series are scheduled for 11 a.m. to 12:30 p.m. Mountain Time.

Western and DOE’s Office of Indian Energy Policy and Programs and Tribal Energy Program have teamed up to present the webinars. Don’t miss these events if you are looking for ways to promote tribal energy sufficiency and foster economic development and employment on tribal lands through renewable energy and energy efficiency technologies. You will learn about marketing, transmission, financing, partnerships and much more.

ED5 project completes major milestone

The Transmission Infrastructure Program Electrical District 5 – Palo Verde Hub project in Arizona’s Pinal and Maricopa counties reached a major

ED5 project map

Completion of the 22-mile segment between ED5 and Test Track substations represents nearly half of the new and upgraded line construction needed to complete the project.

construction milestone recently with the completion of 22 miles of new 230-kilovolt transmission lines between ED-5 substation and Test Track substation.

The new segment of transmission line represents half of all new construction and line upgrades required for the project, which will increase transmission capacity to deliver renewable energy, primarily solar, to consumers in Arizona, southern Nevada and southern California.

Construction was completed three weeks ahead of schedule, saving Western and the project proponent money and keeping the project on track for early 2015 energization.

The next step in the project is to expand Test Track substation to accomodate the increased transmission capacity. At the same time, the other half of transmission line upgrades will continue through early 2014.

Wind generates awards

Western’s service area is in the heart of our Nation’s renewable energy potential. Nine of the 10 windiest states in the Nation are in our geographic footprint. So it makes sense for Western to partner with the Department of Energy’s Wind Powering America initiative to present awards to public-owned utilities and cooperatives for their leadership in promoting wind energy development.

On Feb. 22, East River Electric Cooperative in Madison, S.D., received the Wind Cooperative of the Year Award for generation and transmission cooperatives at the National Rural Electric Cooperative Association TechAdvantage Conference in New Orleans.

East River, a Western customer serving eastern South Dakota and western Minnesota, earned the award by creating a model for community-based, locally owned wind development that relied on South Dakota citizens rather than large equity investors.

Also, Western and DOE’s Wind Powering America initiative are currently accepting nominations for the 2013 Public Power Wind Award in partnership with the American Public Power Association.  Nominations are due March 25. See the news release for more information.

This is the eleventh year for the Public Power Wind Award and the twelfth for the Wind Cooperative of the Year Award. You can see the year-by-year progression on installed wind capacity in the United States in an animated map on Wind Powering America’s website.

Construction work starts on ED5-PVH Project

3 employees work in a trench on substation footer

Employees with Tri-Technic Inc. prepare footer for an ED-5 Substation retaining wall, Feb. 11, 2013.

Construction work started on a project that will connect renewable energy south of Phoenix, Ariz., to a major trading hub. This is the first major construction step for the Electrical District No. 5 – Palo Verde Hub Project.

“It’s great to see that construction work has started on this important project,” said ED5-PVH Project Manager Todd Rhoades. “Hurricane Sandy and the recent northeast blackouts really highlight how important our energy infrastructure is to our everyday lives. This project is an investment in improving our system in the desert southwest area.”

Western awarded the construction contracts in fall 2012. These projects are being funded through Western’s Transmission Infrastructure Program.

What benefits do you see from projects like ED5-PVH in support of the utility industry?

Southline environmental analysis moves forward

Environmental review and analysis of transmission line projects is an iterative process. A project is proposed; the proposal is reviewed; alternatives are developed; comments are solicited and considered; revisions are made. Then the process repeats.

The Southline Transmission Line Project  provides a great example. The Bureau of Land Management New Mexico  and Western  are co-lead agencies preparing the environmental impact statement for the project. The BLM recently completed meetings with Federal, state and county agencies as part of the process of developing alternatives for the project.

These meetings were an opportunity for the agencies to review the preliminary alternative routes being considered by the BLM and Western for the project and identify concerns and issues with any of the alternative routes. Input from the agencies will be included in the final alternatives development report and keeps the environmental analysis moving forward on schedule.

The BLM and Western expect to complete a draft EIS later this year. That’s when the public will have a chance to review and comment on the draft EIS. Those comments will then be considered as the agencies develop a final EIS.

Have you ever wanted to know more about the National Environmental Policy Act, or NEPA, process and how Federal agencies analyze projects? Here’s a chart that shows the steps in the process. You can also learn more in the NEPA section of the Department of Energy’s website.

Rim Rock Wind Farm achieves commercial operation

A wind turbine

A Rim Rock Turbine generates energy in Montana. (Photo by NaturEner)

Western’s Connections blog first shared that the Rim Rock Wind Farm’s planned to interconnect through the Montana Alberta Tie Limited transmission line (a project supported through Western’s Transmission Infrastructure Program) in a post last Jan. 10, 2012. Even though Western’s involvement with MATL was completed last fall, the wind farm announced another milestone yesterday.

NaturEner publicized Jan. 10 that the commercial operations of its Rim Rock Wind Farm near Kevin, Mont., started Dec. 28, 2012. Read more »

Regional utilities gather in Colorado to talk energy efficiency

More than 100 electric utilities and industry representatives attended the sixth annual Rocky Mountain Utility Efficiency Exchange in Aspen, Colo., Oct. 10 to12.

Ron Ebenkamp, Tri-State Generation and Transmission Association, invites Robin O'Day, San Isabel Electric; Ray Pierotti, La Plata Electric; Gary Myers, Poudre Valley; and Craig Tate, Holy Cross Energy, to discuss the major role lighting programs continue to play in utility energy-efficiency portfolios at the sixth annual Rocky Mountain Utility Efficiency Exchange in Aspen, Colo., Oct. 10. The networking event lasted three days and allowed local water and energy utilities to share best practices in efficiency, renewable energy, demand response and key account customer management programs.

Ron Ebenkamp, Tri-State Generation and Transmission Association, invites Robin O'Day, San Isabel Electric; Ray Pierotti, La Plata Electric; Gary Myers, Poudre Valley; and Craig Tate, Holy Cross Energy, to discuss the major role lighting programs continue to play in utility energy-efficiency portfolios at the sixth annual Rocky Mountain Utility Efficiency Exchange in Aspen, Colo., Oct. 10.

Co-sponsored by Western’s Energy Services office, the networking event provided energy and water utilities serving Colorado and neighboring states an open forum to learn and teach how to implement efficiency, renewable energy, demand response and key account customer management programs with their peers.

Read more »

NaturEner holds ceremony for Rim Rock wind farm in Montana

Rim Rock wind turbine

Rim Rock wind turbine owned and operated by NaturEner (Photo provided by NaturEner website)

Hundreds of people attended NaturEner’s opening ceremony Sept. 14 for the Rim Rock wind farm just north of Cut Bank, Mont., to celebrate overcoming the considerable challenges in making the wind farm a reality.

“There was a time last summer when we were doubtful we were going to be able to pull this off,” said Greg Copeland, Development Director of the U.S. division of the Spanish-owned NaturEner. Read more »

Customers: Send comments about Defining the future’ by Aug. 17

The Department of Energy and Western Joint Outreach Team finished the final two of six public workshops and listening sessions the week of July 30 to define Western’s role in transitioning the grid to a flexible, reliable system worthy of the 21st century.

But the team is still accepting comments through Aug. 17 for stakeholders and Aug. 24 for Native American Tribes as part of the public scoping process for this effort. Some comments submitted are already available for viewing on Western’s website. To get your comment in, email JOT@wapa.gov with your name, organizational affiliation and your thoughts.

The team will take the oral and written comments and ideas generated in the workshops and submitted via email to draft recommendations for public comment sometime this fall.

Here are some photos from the Aug. 2 meeting in Sioux Falls, S.D.

Western conducted grid reliability webinar

Western Area Power Administration conducted a Grid Reliability—Impacts to Tribal Renewable Projects webinar in partnership with the U.S. DOE Office of Indian Energy Policy and Programs and DOE Tribal Energy Program July 25.

About 55 Tribal members and interested parties participated in the webinar with 112 registering for the event. Western’s Reliability Compliance Program Manager was the featured speaker, covering topics such as key definitions, reliability organizations, oversight process, standards and enforcement among other reliability considerations. 

Western’s Renewable Resource Program Manager Randy Manion shared, “This webinar was the eighth in the Fiscal Year 2012 Tribal Webinar series coordinated by Western. Laurent Weber, Western’s Reliability Compliance Program manager, did a masterful job explaining complex issues.”

The webinar series is giving Western transmission and power marketing experts a platform to share their incredible knowledge and expertise with Tribal representatives, renewable energy developers and other important stakeholders.